Drainage Alteration Works — Civils, Liverpool
Drainage alteration works on a Liverpool site delivered to a fast 12-week programme. Front-loaded cost planning and rapid valuation cycles kept pace with on-site progress, with significant value moved through in a short window. Outcome: Works delivered on programme. Accounts closed within two weeks of practical completion.
Project Value
£650k
Duration
12 weeks
Project Scope
On budget
Client:
Confidential
Location
Liverpool, UK
Sector
Civils
Completion
2025
The Challenge
A fast-track drainage package on a live site demanded front-loaded commercial planning and rapid decision-making throughout.
Delivering a complex drainage package on a compressed 12-week programme
Maintaining cost certainty under significant programme pressure
Closing the final account rapidly after practical completion
Our Approach
01
Front-Loaded Cost Planning
Full cost plan front-loaded before works commenced to establish clear commercial parameters from day one.
02
Rapid Valuation Cycles
Rapid valuation cycles maintained throughout to keep the client fully informed under programme pressure.
03
Fast Final Account
Final account agreed and closed within two weeks of practical completion.
Key Performance Metrics
£650k
Groundworks package value
12
Weeks — delivered on programme
2
Weeks to close final account after PC
Technology & Tools
Cost Planning
Front-loaded commercial framework
Drainage
Fast-track civils package
Final Account
Closed within 2 weeks of PC
"Fast-track drainage done properly — cost was under control throughout and the final account was wrapped up immediately after handover."
Client Representative
Civils Sector, Liverpool