Warehouse Alterations — Industrial, Birmingham

Major drainage, soakaway, and external concrete yard installation for a Birmingham-based transport operator on a fully operational site. Pinehurst provided cost planning, procurement support, monthly valuations, and final account negotiation. Approach: Works phased to keep the transport yard running throughout — half the site operational at any one time. Outcome: Programme delivered without hindering the client's wider transport operations.

Project Value

£1.1m

Duration

60 weeks

Project Scope

On programme

Client:

Confidential

Location

Birmingham, UK

Sector

Industrial

Completion

2025

The Challenge

Delivering major groundworks on a fully operational transport yard meant the site could never fully close, so commercial control and careful phasing had to run alongside live operations throughout a long programme. - Installing drainage, soakaway, and a new external concrete yard while the transport operation remained live - Keeping the yard working throughout, with only half the site available at any one time - Maintaining cost certainty and commercial control across an extended 60-week programme

Installing drainage, soakaway, and a new external concrete yard while the transport operation remained live

Keeping the yard working throughout, with only half the site available at any one time

Maintaining cost certainty and commercial control across an extended 60-week programme

Our Approach

01

Cost Planning & Procurement Support

Full cost planning established commercial parameters up front, with procurement support to secure the right packages for the groundworks and concrete works.

02

Monthly Valuations

Monthly valuations ran throughout the 60-week programme to keep the client fully informed and costs under control on a live, phased site.

03

Final Account Negotiation

Final account negotiated and agreed on completion, closing out the commercial position cleanly.

Key Performance Metrics

£1.1m

Groundworks package value

60

Weeks delivered on a live, phased site

2025

Completed without hindering transport operations

Technology & Tools

Cost Planning

Commercial parameters set up front

Procurement Support

Securing groundworks and concrete packages

Valuations & Final Account

Monthly valuations to clean closure

Construction Consultancy

Start Your Project Discussion

Speak with our team to explore how AI-driven construction consultancy can support your project planning and cost decisions.

Construction Consultancy

Start Your Project Discussion

Speak with our team to explore how AI-driven construction consultancy can support your project planning and cost decisions.

Construction Consultancy

Start Your Project Discussion

Speak with our team to explore how AI-driven construction consultancy can support your project planning and cost decisions.